Construction continues to move forward at Colliery Parc, with several key milestones reached over the past week and more activity planned across the site. From completed roof framing to upcoming utility work and the next phase of building installation, here's the latest look at what's happening on site.
A milestone worth celebrating! Since our last update, roof framing on Building 3 is officially complete. The framing crew has now moved on to finishing the decks, while roofing materials have been delivered to the roof. Roofers are expected to begin installing shingles over the coming week, weather permitting.
The foundation walls for Building 5 have been formed, poured and stripped, and the roof trusses have arrived on site. The next steps include waterproofing and insulating the foundation before backfilling begins. This work will require some excavation equipment on site over the next week or so.
Work is progressing toward the next stage of construction. Roof framing on Building 6, located on the east side of the site, is expected to begin within the next couple of weeks.
On November 25, we'll also be craning the next building into place, marking the final building installation for this phase. Additional modules are expected to arrive next week as we prepare for the installation.
Vinyl decking installation on Building 3 is expected to begin within the next couple of weeks. As mentioned in our previous update, this work will require temporary hoarding and heaters to maintain suitable working temperatures.
We'll take steps to shroud the heating equipment wherever possible to help minimize noise and keep the duration of this work as short as possible.
Concrete work for the Building 3 patios is expected to follow, so residents can anticipate some additional activity and concrete truck traffic around that time.
Siding installation on Building 3 is still a few weeks away. This work will involve some use of the surrounding roadways. We'll share more information and timing details as the schedule is confirmed.
Work on shallow utilities, including power, gas and communications lines, is expected to begin within the next couple of weeks and continue into December.
Later this month, utility crews are also expected on site to install and connect the electrical and gas meters for Buildings 5 and 6. We'll provide an update if this work is expected to affect nearby sidewalks or roadways.
Our deep utilities contractor is tentatively scheduled to return to the site in early December to complete the remaining work. We'll confirm the timing once the schedule is finalized.
Construction has officially started on the Centennial Park Bus Stop. The work is expected to take approximately one week, with some temporary disruption in the area. We apologize for any inconvenience and appreciate everyone's patience while these improvements are completed.
With construction activity increasing over the coming weeks, please use extra caution when travelling around Colliery Parc.
There will be several active work areas, including overhead roofing work, excavation equipment, utility crews, deliveries and a crane on site later this month.
Please stay clear of all fenced and marked construction zones, watch for moving equipment and follow posted safety signage.
Thank you for your continued patience and cooperation as we work toward bringing Colliery Parc to life. We'll keep sharing regular updates as construction progresses!