Buildings 3, 5 and 6 Take Shape

November 13, 2026

Construction Update: Building Progress and What's Coming Next at Colliery Parc

Construction continues to move forward at Colliery Parc, with several key milestones reached over the past week and more activity planned across the site. From completed roof framing to upcoming utility work and the next phase of building installation, here's the latest look at what's happening on site.

On-Site Building Construction

Building 3: Roof Framing Complete!

A milestone worth celebrating! Since our last update, roof framing on Building 3 is officially complete. The framing crew has now moved on to finishing the decks, while roofing materials have been delivered to the roof. Roofers are expected to begin installing shingles over the coming week, weather permitting.

Building 5: Foundation Progress

The foundation walls for Building 5 have been formed, poured and stripped, and the roof trusses have arrived on site. The next steps include waterproofing and insulating the foundation before backfilling begins. This work will require some excavation equipment on site over the next week or so.

Looking Ahead: Building 6 and the Final Modules

Work is progressing toward the next stage of construction. Roof framing on Building 6, located on the east side of the site, is expected to begin within the next couple of weeks.

On November 25, we'll also be craning the next building into place, marking the final building installation for this phase. Additional modules are expected to arrive next week as we prepare for the installation.

Decking and Patios: Coming Up Next

Vinyl decking installation on Building 3 is expected to begin within the next couple of weeks. As mentioned in our previous update, this work will require temporary hoarding and heaters to maintain suitable working temperatures.

We'll take steps to shroud the heating equipment wherever possible to help minimize noise and keep the duration of this work as short as possible.

Concrete work for the Building 3 patios is expected to follow, so residents can anticipate some additional activity and concrete truck traffic around that time.

Coming Soon: Building 3 Siding

Siding installation on Building 3 is still a few weeks away. This work will involve some use of the surrounding roadways. We'll share more information and timing details as the schedule is confirmed.

Public Construction Updates

Shallow Utilities and Meter Installation

Work on shallow utilities, including power, gas and communications lines, is expected to begin within the next couple of weeks and continue into December.

Later this month, utility crews are also expected on site to install and connect the electrical and gas meters for Buildings 5 and 6. We'll provide an update if this work is expected to affect nearby sidewalks or roadways.

Deep Utilities

Our deep utilities contractor is tentatively scheduled to return to the site in early December to complete the remaining work. We'll confirm the timing once the schedule is finalized.

Centennial Park Bus Stop

Construction has officially started on the Centennial Park Bus Stop. The work is expected to take approximately one week, with some temporary disruption in the area. We apologize for any inconvenience and appreciate everyone's patience while these improvements are completed.

A Reminder About Site Safety

With construction activity increasing over the coming weeks, please use extra caution when travelling around Colliery Parc.

There will be several active work areas, including overhead roofing work, excavation equipment, utility crews, deliveries and a crane on site later this month.

Please stay clear of all fenced and marked construction zones, watch for moving equipment and follow posted safety signage.

Thank you for your continued patience and cooperation as we work toward bringing Colliery Parc to life. We'll keep sharing regular updates as construction progresses!

‍

Colliery Parc on FacebookColliery Parc on X

Related News

Construction Updates

November Progress & Upcoming Milestones

Read More >
Promos

12 Months of No Mortgage Payments at Colliery Parc

Read More >

Secure your forever in Canmore. Sign up today.

🇺🇸
 
By clicking “Submit,” you agree to Avalon using your information to respond to your inquiry.
Thanks for submitting the form.
You're in.

I’ll send you a quick breakdown shortly so you can get a clear sense of how Colliery Parc actually works — and whether it’s the right fit.

If something already stood out, just reply to the email when it comes through — I read everything.

If you left your number, I’ll follow up by text shortly.
Oops! Something went wrong while submitting the form.

The best place to live, in the best place to live

Find your home