Construction continues to progress at Colliery Parc, with crews working on several buildings throughout the site and upcoming milestones planned for the weeks ahead. Here's a look at what's happening on site, what's coming next, and a few important updates regarding public construction.
Last week, we shared that framing crews had moved on to the decks at Building 3. That work is now complete, and roofing crews are currently installing shingles. Roofing is expected to continue into next week, weather permitting.
The Building 5 foundation has been waterproofed and has successfully passed its backfill inspection. Backfilling is now underway and is expected to be completed next week. You may notice excavation equipment on site for the next few days as this work wraps up.
The final building of this phase is scheduled to be craned into place on Wednesday, November 25. The crane will be set up on site a couple of days in advance.
Once the modules are in place, crews will begin connecting the building's plumbing and electrical systems.
Roof framing on Building 6, located on the east side of the site, is scheduled to begin around this time and continue into December.
Vinyl decking installation at Building 3 is planned for next week. This work will require temporary hoarding and heaters to maintain suitable working temperatures. We will do our best to enclose the heating equipment, minimize noise and keep the duration of this work as short as possible.
Concrete work for the Building 3 patios is expected to follow, so residents can expect some concrete truck activity around that time.
Siding materials for Building 3 are expected to arrive in early December, with installation to follow. This work will involve some use of the road. We'll provide additional details as the schedule is confirmed.
Crews are working hard to complete the bus stop improvements. We are planning to pour concrete on Monday, November 23, with the goal of reopening the road approximately one week later, following the required curing period.
Our deep utilities contractor is tentatively scheduled to return to site in early December to complete the remaining work. We'll provide an update once the return date is confirmed.
Work on shallow utilities, including power, gas and communications lines, is now anticipated to take place later in December and into January.
We'll share more information closer to the start of this work, including any potential impacts to sidewalks or the street.
Please continue to stay clear of fenced and marked construction areas and remain alert for equipment, deliveries and active work zones.
Next week will be particularly busy, with the Building 5 crane and module delivery, roofing crews working overhead, excavation equipment and utility crews on site. Please follow any directions from our construction team, especially around crane operations and delivery areas.
Thank you for your continued patience and cooperation as construction progresses at Colliery Parc. We appreciate your support as we work toward bringing this community to life.