Construction at Colliery Parc continues to move forward as we make steady progress on Phase One. With our third crane now complete, we're continuing to bring modular homes to the site in preparation for the final crane of this phase. Our current target date is November 5, and foundation work remains on schedule.
We're excited to see the next stage of construction taking shape, with roofing work now underway on Building 3 (B3). This is an important milestone as the community continues to come together. The work requires a road use permit, which has been secured through the Town of Canmore. We anticipate completing this portion of the work by the end of November.
We're also planning to begin work on the 5th Street Centennial sidewalk toward the end of the month. Our goal is to have the entire area completed before winter weather fully sets in.
One ongoing challenge has been higher-than-expected groundwater levels, which continue to delay completion of the deep utilities. As a result, we anticipate returning to complete the remaining 5th Street work later this year.
Despite these challenges, progress at Colliery Parc continues, and we're looking forward to sharing more milestones as Phase One takes shape.